Projects lists the portfolio — every project you can see, in one table.
Header
Section titled “Header”Under META PLANNING · PORTFOLIO, the section tabs are Project, Plan, Work items, Agile and Content; within Projects they are All projects, Overview and Activity. Views switches saved views, New project creates one, and Search filters the list.
KPI cards
Section titled “KPI cards”| Card | Counts |
|---|---|
| ALL PROJECTS | Every project in scope. |
| ACTIVE | Projects with status active. |
The table
Section titled “The table”| Column | Meaning |
|---|---|
| Identifier | The project key, for example apollo. |
| Name | The project name. |
| Status | active, on hold, closing, closed. |
| EVM | Earned-value mode — money for projects tracked financially, none otherwise — see How EVM works. |
Use the ⋮ on a row for its actions.